Current on-going Canal Gardens (CG) improvements and beautification projects
Work Started & Completed
06 September - Spikes installed at the low lying perimeter wall along Road L
08 September - Commencement of the perimeter wall painting (60% completed @ 30 Sept)
23 September - Commencement of jogging track along Road P to M, works completed on 28 September
28 September - Fogging carried out in CG
05 October - Work on the rear entrance (jogging track) at the exit of Canal Gardens
Work to Start Soon
1. Pruning of trees at the edge of the canal, awaiting L/A to be given.
2. To apply goat manure to the plants and trees and the planting of more trees and plants; an ongoing landscaping project.
3. To build concrete bollards at Roads G, R, S and T to prevent vehicles from taking shortcuts causing damage to the grasses and the park.
Reported by ~ Property Manager, Hicom Gamuda ~